Prioritization
Prioritization is choosing what not to do. Start from the goal, compare ideas with a simple model like RICE, and look at the cost of delay when time matters. Scores help a conversation, they do not make the decision. Every yes is a no to something else, so say no clearly, with reasons, and keep the door open.
Author: bezzad
Contents
The problem: forty “urgent” requests
It is the start of the quarter in our online shop. The product manager opens the request list. There are forty items:
- Sales wants bulk discounts for office customers.
- Marketing wants a landing page for the Nowruz campaign.
- Support wants a better “Where is my order?” page, because half of the calls are about that.
- The CEO saw a competitor’s “see it in your room” feature and wants one too.
- Engineering wants to upgrade the old payment library.
Everyone says their item is urgent. The team can build maybe five of them this quarter. Whatever the product manager chooses, most people will hear “no”.
This is normal. Prioritization is choosing what not to do. The goal is not to make everyone happy. The goal is to spend the team’s limited time where it creates the most value, and to explain the choice so people can trust it.
Start from the goal, not from the list
A list of requests has no direction. So the first question is not “which request is best?” It is “what are we trying to achieve this quarter?”
For our shop, leadership and the team agreed on one outcome: more customers make a second purchase within 90 days.
Now the list looks different:
- Some requests clearly help the goal. A better order tracking page builds trust, and trust brings people back.
- Some do not help it. Bulk discounts for offices may be a good idea, but they serve another goal.
- Some must be done anyway. The payment library is close to the end of its support. This is a risk, not a feature. It does not compete in the same race.
RICE: a simple way to compare
When several ideas serve the same goal, we need a way to compare them. One popular model is RICE. The team at Intercom created it. It has four parts:
- Reach. How many people will this touch in a fixed time? For example, customers per quarter. Use real data if you have it.
- Impact. How much will it move the goal for each person? Intercom uses a fixed scale: 3 for massive, 2 for high, 1 for medium, 0.5 for low and 0.25 for minimal.
- Confidence. How sure are we about the numbers above? 100 percent for high, 80 percent for medium, 50 percent for low. This part punishes ideas that rest only on enthusiasm.
- Effort. How much work it needs from everyone: product, design and engineering. Intercom counts it in person-months.
The score is reach times impact times confidence, divided by effort. Let’s score four ideas for our goal:
| Idea | Reach (per quarter) | Impact | Confidence | Effort (person-months) | Score |
|---|---|---|---|---|---|
| Delivery date on the product page | 20,000 | 0.5 | 80% | 1 | 8,000 |
| One-click reorder | 3,000 | 2 | 80% | 1.5 | 3,200 |
| Share button for gifts | 4,000 | 1 | 80% | 2 | 1,600 |
| “See it in your room” view | 6,000 | 2 | 50% | 6 | 1,000 |
What does this table tell us?
- A small idea can win. The delivery date has a low impact for each person. But it touches almost every visitor and costs little.
- Low confidence costs a lot. The room view sounds exciting. But we have no evidence yet, and it is the most expensive. Maybe it needs a cheap discovery test first, not a team for six months.
- The numbers open a conversation. If someone disagrees, we can talk about one number: “Why do you think the impact is 2?” This is easier than fighting about whole ideas.
The limits of scoring
A scoring model is a tool for thinking. It is not a machine that makes decisions. Its limits:
- The numbers are guesses. “Impact 2” is an opinion written as a number. A score of 3,200 looks exact, but it is not.
- It is easy to game. If someone wants their idea to win, they can raise its reach or its confidence a little. Ask “where does this number come from?”
- Units must match. If one idea counts reach per month and another per quarter, the table is wrong. Use one time period for every row.
- It ignores dependencies. Sometimes idea B is only possible after idea A.
- It ignores strategy. A new market or a big bet may score low today and still be the right choice.
- It ignores must-do work. Legal rules, security fixes and end-of-support upgrades do not go into the race. They get their own capacity.
Cost of delay: when time matters
RICE does not ask “what happens if we do this later?” For some ideas, the answer is “nothing much”. For others, waiting is very expensive.
Cost of delay is the value we lose for each week the idea is not live. Don Reinertsen made the idea popular in product development. Some examples from our shop:
- The Nowruz landing page loses its whole value if it comes after Nowruz.
- A legal requirement with a deadline may bring a fine after that date.
- A small checkout improvement loses a little every week, at a steady rate.
When two ideas compete for the same team, a simple rule helps. Divide the cost of delay by the duration of the work. This is sometimes called CD3 (cost of delay divided by duration). Do the higher one first.
- The Nowruz page costs 2,000 dollars for each week of delay and takes 1 week. Its CD3 is 2,000.
- Better search costs 5,000 dollars for each week of delay and takes 4 weeks. Its CD3 is 1,250.
- Nowruz first: better search waits 1 week. The cost is 5,000 dollars.
- Search first: the Nowruz page waits 4 weeks. The cost is 8,000 dollars, and Nowruz may already be over.
So the bigger idea is not always first. A short job with a high cost of delay should usually go first.
Opportunity cost: every yes is a no
The team has a fixed amount of time. So when we say yes to one thing, we say no to everything else that could use that time. This is opportunity cost.
This is why “it is only a small request” is a trap:
- Small requests add up. Ten “small” items can fill a whole sprint.
- Switching costs time. Each new item interrupts the work in progress.
- The real question is not “is it good?” Almost every request is good. The question is “is it better than what we will stop doing for it?”
When you show a trade-off, make it concrete: “If we build bulk discounts this month, the reorder button moves to next quarter.”
Saying no
A product manager says no much more often than yes. How you say it matters a lot.
Bad
“No, it is not on the roadmap.”
- It gives no reason.
- It sounds like a closed door.
- The person goes to your boss.
Good
“Thank you, I understand that office customers ask for this. This quarter we focus on second purchases, and this does not move that goal. I wrote down the request and the three customers who asked. If more office customers ask, or our goal changes, we will look at it again in the next planning. Can I see the deals that depend on it?”
A good no has these parts:
- Show you understood. Repeat the problem in your own words.
- Connect it to the goal. The reason is the shared goal, not your personal taste.
- Say “not now” when it is true. Many requests are good, just not for now.
- Keep a record. Write the request, who asked, and the evidence. Repeated requests become data.
- Offer what you can. A workaround, a smaller version, or a date for the next review.
Common mistakes
| Mistake | Result | Right way |
|---|---|---|
| Prioritizing the request list without a goal | Whoever shouts loudest wins. | Agree on the outcome first, then rank. |
| Trusting the score as exact | False precision and gaming. | Use scores to start a conversation. |
| Mixing time units for reach | The table compares wrong numbers. | One time period for every row. |
| Putting must-do work in the scoring race | Legal and security work keeps losing. | Give must-do work its own capacity. |
| Ignoring cost of delay | Urgent short jobs come too late. | Ask what waiting costs, and use CD3. |
| “It is only small” | Small items fill the whole sprint. | Every yes is a no to something else. |
| A no with no reason | People go around you. | Explain the goal, say “not now”, keep a record. |
Summary in six lines
- Prioritization is choosing what not to do.
- Start from the goal. Prioritize problems before solutions.
- RICE compares ideas: reach times impact times confidence, divided by effort.
- Scores are guesses. Use them to ask questions, not to decide alone.
- When time matters, look at the cost of delay and do short, urgent jobs first.
- Every yes is a no. Say no clearly, tie it to the goal, and keep a record.