Practice exam
For each question, think first or write your answer. Then open the answer and mark yourself honestly. The result stays only in your browser.
/ 14
1. The one-on-one notes you inherit
Question: You are the new team lead of an online shop team. The previous lead moved to another team. You read the notes from his last one-on-ones with Neda, a developer on the team. Each meeting took about ten minutes:
2026-07-01 Checkout ticket: 70%. Done on Friday.
2026-07-15 Checkout done. Started stock alerts.
2026-07-29 Stock alerts: waiting for an API from the warehouse team.
2026-08-12 Stock alerts done. Next: invoices.
2026-08-26 Invoices: 50%. No blockers.
2026-09-09 Invoices done. Neda: "all fine".
2026-09-23 Cancelled (lead busy with the release).
What do you think about these meetings? What would you do with your own one-on-ones with Neda?
Short answer: These are status reports, not one-on-ones. Every line is about tickets, and the board already shows all of it. There is nothing about Neda herself: her problems, her growth, feedback in either direction. There are no agreed actions, and the last meeting was cancelled. I would keep the rhythm, but make the meeting Neda’s meeting: her topics first, open questions, feedback both ways, and a short shared note with actions.
Hint (if the candidate says there is no problem): Which of these lines could the lead not have read on the board? And a month later, Neda tells you she is talking to another company.
What is missing? (step by step)
- Information that only a one-on-one gives. Is Neda bored, stuck, overloaded, unhappy with someone? Nothing here can show it.
- Growth. No word about what Neda wants to learn or where she wants to be in a year.
- Feedback. Not from the lead to Neda, and not from Neda to the lead.
- Actions. Nothing was agreed, so nothing can be checked next time.
- A signal of importance. The meeting was cancelled for a release. The message Neda hears is “you come after the work”.
“All fine” after six short status meetings usually does not mean all is fine. It often means “this is not the place to say it”.
What I would do:
- The first meeting is a get-to-know meeting. “How do you like to work? What do you enjoy most in your work? What frustrates you? How do you like to get feedback? What did the previous lead do that helped you, and what did not?”
- A shared document. Both of us add topics during the week. Her topics come first in the meeting.
- Status goes to the board. If I need a ticket update, I ask in the stand-up or in the chat, not in her one-on-one.
- A few open questions when she has no topics. “What is slowing you down? What would you change in the team if you could?”
- Ask for feedback about myself, with a concrete question, from the first weeks.
- Write down actions and start the next meeting by checking them.
- Never cancel. Move it if needed.
- After about a month, plan a separate, longer career conversation.
Follow-up question: Neda says: “Honestly, I have nothing to talk about. Can we skip these meetings?”
Follow-up answer:
- Respect it, but do not drop the meeting completely. Without a regular slot, problems come to you only when they are already big.
- Make it lighter instead: shorter, or every two weeks instead of every week.
- Bring better questions. “Nothing to talk about” often means the earlier meetings taught her that only status was welcome.
- Bring your own useful topics: context from the company, feedback on her work, a chance to own something new.
- Trust takes time. If the meeting is useful a few times, she will start bringing topics.
Red flag: Thinks the notes are fine because “the work gets done”, or plans to use the one-on-ones to check deadlines more closely.
2. A feedback message before the half-year review
Question: It is September. Next week is the half-year review. You are the team lead, and you plan to send this message in chat to Omid, a developer on your online shop team. The events you have in mind happened in March and April:
Hi Omid, I want to give you some feedback before the review.
In general you need to be more of a team player and take more ownership.
Sometimes your attitude in code reviews is not great.
Overall you are doing OK. Let's keep improving!
What do you think about this feedback? Would you send it?
Short answer: I would not send it. It is vague (Omid cannot tell what to change), it is made of judgments (“attitude”, “team player”) instead of facts, it is six months late, and criticism goes through a chat message right before a review. I would talk to Omid in person, soon after each event, using Situation, Behavior, Impact, and end with a question.
Hint (if the candidate says there is no problem): Imagine you are Omid. After reading this message, what exactly will you do differently tomorrow morning?
What is wrong with it? (step by step)
- No situation. Which review? Which ownership? Omid has to guess, and he will probably guess wrong.
- Judgments, not behavior. “Attitude is not great” is a label on the person. People defend themselves against labels. They can change behavior.
- No impact. Why does it matter? Without the impact, it sounds like personal taste.
- Too late. Events from March cannot be fixed now, and Omid will ask: “Why did nobody tell me then?”
- The wrong channel. Criticism in a short chat message is easy to misread, and he cannot ask questions.
- A mixed message. “Doing OK” at the end makes it unclear if there is a real problem.
The fix: specific, early, in person
Say it in a private conversation, close to the event. For example, about one review:
Situation: In the review of Mina's cart PR last Tuesday,
Behavior: you wrote "this is wrong, rewrite it" and did not say why
or what to change.
Impact: Mina waited two days and did not know what to fix.
The cart release moved to the next sprint.
Question: How do you see it?
And for “ownership”, find the real behavior behind the word. For example: “The stock alert broke in production on Monday. You saw the alert in the channel, but you did not pick it up or tell anyone, even though it was your feature. I want the person who built a feature to be the first to respond to its alerts.”
Also say clearly what is going well, with the same level of detail. And for the half-year review: nothing in it should be a surprise. If something was never discussed before, it is the lead’s mistake, and the review should say so honestly.
Follow-up question: Omid answers: “That comment was fine. Mina is just too sensitive.”
Follow-up answer:
- Do not argue about Mina’s personality or about Omid’s intention. Stay with the behavior and its impact: “Maybe you meant it well. The impact was still two days of waiting.”
- Listen. Maybe Omid was overloaded with reviews that week, which is a team problem too.
- Agree on the expectation, not on who is right: “When you ask for a change in a review, say why and suggest a direction.”
- Consider a team agreement for review comments, so it is not only about Omid.
- Check later: look at his next reviews and give positive feedback when it gets better.
Red flag: Thinks the message is fine because “it is honest”, or prefers to give no feedback at all to avoid conflict, or keeps the feedback for the review document only.
3. Retrospectives that the team wants to cancel
Question: You lead an online shop team of five developers with two-week sprints. These are the notes from the last four retrospectives:
Sprint 21 Went badly: reviews are slow.
Action: review faster.
Sprint 22 Went badly: reviews are slow; too many meetings.
Action: try harder on reviews.
Sprint 23 Went badly: reviews are slow; urgent bugs from support.
Action: communicate better.
Sprint 24 Went badly: reviews are slow.
Action: (no time, the retro was cut to 15 minutes)
In the stand-up, Reza says: “Retros are useless. Nothing changes. Let’s cancel them and use the hour for coding.” Two others agree. What do you think? What would you do?
Short answer: Reza is right that nothing changes, but the cause is not the meeting. The cause is the actions: “review faster” and “communicate better” are wishes, not actions. They have no owner, no date, and nobody checks them at the next retro. I would keep the retro, start it by checking the last actions, use data to understand why reviews are slow, and leave with one or two concrete actions that have an owner, a date, and a place on the board.
Hint (if the candidate says there is no problem): Who was supposed to do “review faster”, and by when? How would anyone know if it was done?
Why does nothing change? (step by step)
- The actions are not actions. Nobody can do “try harder” on Monday morning.
- No owner. When everyone owns an action, nobody does.
- No check. No retro starts with “did we do what we decided?”
- No look at the cause. “Reviews are slow” is a symptom. Why are they slow? Big PRs? Everything waits for one person? Nobody has time because of support bugs? Each cause has a different fix.
- The team learns retros do not matter, so the retro gets cut, and then the team wants to cancel it.
What I would do:
- Agree with the team, not against them. “You are right that nothing changed. Let’s try a different way for two sprints. If it still does not help, we change the format or the rhythm.”
- Bring data. For the last month: how long a PR waits for its first review, the size of PRs, and who does the reviews.
- Spend the time on one problem, the one that came back four times.
- Choose one or two concrete actions. For example: “Mina sets up a review rotation, starting Monday”, or “Before starting a new ticket, everyone checks the review column first”, or “PRs over 400 changed lines are split”.
- Put the actions on the board like any other work.
- Start the next retro with them. Done? Did it help? If not, why?
- Protect the time. A retro cut to 15 minutes because of work tells the team it is not important.
Follow-up question: The data shows the average PR waits 2.5 days for a first review, and 80% of reviews are done by you, the lead. What now?
Follow-up answer:
- Then the lead is part of the cause. Say it openly in the retro. It builds trust.
- Change the rule: any two team members can approve a PR. The lead reviews only risky areas.
- Pair people on the areas where only the lead knows the code, so more people can review them.
- Measure again after two sprints and show the result in the retro.
Red flag: Agrees to cancel the retros, or answers with a long list of new actions and rules, or blames the team for not “trying harder”.
4. A lead who asks for more people
Question: You are the engineering manager. Sara leads the online shop team: five developers plus Sara. She sends you these numbers for last month, with a request:
Pull Requests merged: 38
Reviewed and approved by Sara: 38
Average wait for first review: 2.5 days
Production deploys: 6 (all done by Sara)
Sara's meetings: about 22 hours per week
Sara's own tickets: 4 (all hard payment tickets)
3 still open
Sara: "I work evenings to keep up. We need to hire two more developers."
What do you think? What would you suggest to Sara?
Short answer: This is not mainly a headcount problem. Sara is the bottleneck: every PR, every deploy and the hardest tickets go through her. Two more developers would make more PRs waiting in her queue. The fix is to delegate and spread knowledge: any two team members can approve PRs, deploys become automated and run by anyone, Sara stops taking critical-path tickets, and others learn the payment code.
Hint (if the candidate says there is no problem): What happens to these numbers when Sara takes two weeks of holiday?
Why is this a problem? (step by step)
- All work passes through one person. The speed of the team becomes the speed of Sara’s free time, which is small: 22 hours of meetings plus her own tickets.
- Work waits. 2.5 days for a first review means every feature is days later than needed, and developers start new work while they wait, so there is more work in progress.
- Her own tickets are blocked by her other jobs. Three of four hard tickets are still open. The most important work is done by the person with the least focus time.
- The bus factor is one for payments and for deploys. A holiday, an illness, or Sara leaving stops the team.
- The team does not grow. Nobody else learns payments or deploys, because Sara does them.
- More people make it worse. Seven developers write more PRs, and Sara reviews all of them.
What I would suggest:
- Reviews: any two team members can approve. Sara reviews only the risky areas (payments, security), and samples others.
- Deploys: write down the steps, then automate them in the CI/CD pipeline. Anyone on the team can deploy.
- Payments knowledge: the next payment tickets go to other developers, with Sara as a pair or reviewer, not the author.
- Sara’s own code: no tickets on the critical path. She picks work that unblocks others, like tools and test helpers.
- Meetings: check the 22 hours. Which ones can someone else on the team attend?
- Measure again in a month: wait for first review, number of people who can deploy and review payments.
- Then talk about hiring if the team is still short of capacity. Now it is clear what the new people will do.
Follow-up question: Sara says: “But payment code is risky. If someone else approves a PR and misses a bug, it is still my responsibility.”
Follow-up answer:
- She is right that she stays responsible. But responsibility does not mean she must do every review herself.
- A tired reviewer with 38 reviews a month also misses bugs. Quality comes more from the system than from one person.
- Make the system safer: good tests for payments, required CI checks, a short review checklist for payment changes.
- Grow a second payment expert: pair on the next tickets until one more person can review payment PRs alone.
- For a while, Sara can be a second reviewer on payment PRs only, not the only reviewer for everything.
Red flag: Agrees that the answer is hiring, or tells Sara to “manage her time better” or work harder, without seeing the bottleneck.
5. The slow order history page
Question: You lead an online shop team. This is the team chat from last week:
Mon 10:00 Sara (lead): Mina, can you take the order history
page? It's slow.
Thu 16:00 Mina: PR ready. I added an index on (customer_id, created_at)
and the page now loads 20 orders at a time. 8 s -> 0.6 s.
Thu 16:20 Sara: Thanks! I was thinking of a Redis cache instead.
Let me take it from here, I'll do it tonight.
Fri 09:00 Sara merged her own PR (Redis cache). Mina's PR was closed.
Two weeks later, in her one-on-one, Mina says: “Next time, just tell me exactly what you want, and I will do it.” You are Sara. What do you think happened? What would you do?
Short answer: Sara delegated a vague task (no goal, no “done”, no level of authority), and then took the work back even though Mina’s solution solved the problem. Mina learned that her decisions do not count, so she stops owning things. The fix: admit the mistake to Mina, and next time delegate the result: goal, context, limits, what done means, and the level of authority. If the solution is different but not wrong, accept it.
Hint (if the candidate says there is no problem): What was the goal of the task? Did Mina’s solution reach it?
What went wrong? (step by step)
- The task had no goal. “It’s slow” does not say how fast is fast enough. So Sara and Mina had two different pictures of “done”.
- No level of authority. Could Mina choose the solution, or should she show the plan first? Mina assumed she could decide. Sara assumed she would be asked.
- No check-in. A short plan review on Tuesday would have shown the different ideas early.
- The solution was good. 8 seconds to 0.6 seconds with an index and paging is a simple, solid fix. A cache adds new problems: when to clear it, stale data, one more system to run.
- Taking it back killed ownership. The lesson Mina learned is: “Do not think, wait for Sara.” So Sara will get more work, not less.
- Mina’s work was thrown away, and Sara worked another evening.
What I would do:
- Own the mistake with Mina. “I asked you to do this and then took it from you. Your solution met the goal. That was my mistake.”
- Look again at the two solutions together. If the index solution is enough, use it.
- Next time, a clear brief: “The order history page takes 8 seconds. Goal: under 1 second for a customer with 500 orders. No change to the public API. You choose the solution. Show me the plan on Tuesday.”
- Ask “is it wrong, or only different?” before rejecting a delegated solution.
- If something is wrong, say it in the review with a reason, and let the owner fix it.
Follow-up question: What if Mina’s solution really had a serious problem? For example, the index migration would lock the orders table for minutes in production.
Follow-up answer:
- Then it is wrong, not only different. Say it clearly in the review: “This migration locks the orders table. During the day that blocks checkout.”
- Let Mina own the fix. For example, PostgreSQL can build an index without blocking writes (the concurrent option), or the migration can run at a quiet time.
- Pair with her if she has not done this before. It is a good learning moment.
- Take the work over only in a real emergency, and say clearly that it is an exception.
Red flag: Thinks it was fine because the lead’s solution was “better”, or that Mina should simply be more flexible, without seeing the vague delegation.
6. Day 9 of a 10-day sprint
Question: You lead an online shop team of five developers. It is day 9 of a 10-day sprint. The sprint goal is “Gift cards at checkout”. This is the board:
To do: 3 In progress: 12 In review: 7 Done: 2
In progress, by person:
Reza: 3 items
Mina: 2 items
Omid: 3 items (2 are urgent bugs from support)
Arash: 2 items
Neda: 2 items
In review: oldest item waits 5 days
Done: Newsletter fix, Logo update
Gift card items: 6 in total
0 done, 4 in progress, 2 in review
The product manager asks you: “Can we add two developers from another team to finish gift cards?” What do you think? What would you do?
Short answer: The team is not short of people. It has too much work in progress: 12 items open for 5 people, 7 items waiting in review, and interruptions from support. Nothing of the sprint goal is done. Adding people now would add onboarding and even more open work. Today, I would stop starting and finish: the whole team reviews and completes the gift card items. From the next sprint: WIP limits, review before new work, and a rotating shield for support bugs.
Hint (if the candidate says there is no problem): Count the gift card items in the Done column. And how long has the oldest review been waiting?
Why is the sprint failing? (step by step)
- Too many open items. Two or three items per person means everyone switches between tasks, and every switch costs time.
- Review is a queue. Seven items wait in review, one for five days. Starting new work is more fun than reviewing, so the queue grows.
- Interruptions land on one person. Omid has two urgent support bugs on top of his sprint work.
- The goal is spread thin. All six gift card items are started, none finished. At 80% each, customers get nothing.
- More people do not help late. New people need context and someone to explain the code. That time comes from the same busy team. Fred Brooks wrote about this long ago: adding people to a late software project tends to make it later.
What I would do today and tomorrow:
- Stop starting. No new items until the sprint ends.
- Review first. Everyone starts the day by reviewing gift card PRs, oldest first.
- Swarm on the goal. Pairs finish the in-progress gift card items. Non-goal items wait.
- Be honest with the product manager. “We will likely finish part of gift cards. Here is what can ship, and what moves to next sprint.” Bad news early, with options.
What I would change from the next sprint:
- WIP limits. For example, at most 5 items in progress and 3 in review. When review is full, the next free person reviews.
- Smaller items. Each item can be finished and reviewed in one or two days.
- A rotating shield. One person per sprint handles support bugs, so the others can focus. Plan less sprint work for that person.
- Talk about it in the retro, with these numbers.
Follow-up question: How do you choose the WIP limit numbers?
Follow-up answer:
- Start simple, near the team size or a bit lower. For example 5 in progress for 5 people, and 3 in review.
- Watch what happens. If people often have nothing to do, raise the limit a little. If items still wait a long time, lower it.
- The exact number matters less than the rule: when a column is full, you help finish instead of starting.
- Review the limits in each retro, with data like cycle time and how long items wait.
Red flag: Agrees to add more people, asks for overtime, or blames individuals, without seeing the work in progress and the review queue.
7. The incident channel on Black Friday
Question: You lead the online shop team. On Black Friday, checkout failed for many customers. This is the team channel, copied into the postmortem draft:
20:05 Alert: checkout error rate 35%
20:07 Omid: looking
20:09 Mina: me too, checking the DB
20:10 Reza: I restarted payment-service
20:14 Omid: errors dropped! fixed?
20:16 Alert: checkout error rate 38%
20:20 Sara (lead): I'm checking payment-service logs
20:31 Support (other channel): customers say they can't pay.
Anyone?
20:40 Arash: DB looks fine
20:52 Sara: still digging, something in the fraud-check calls?
21:05 Product manager (private message to Sara):
what's going on?? should we tell customers?
21:30 Sara: found it: new-fraud-check flag turned on at 15:10
21:32 Sara: flag off. Error rate back to 0.5%
In the postmortem meeting, someone asks: “How can we respond better next time?” What do you see in this timeline?
Short answer: The team worked hard, but nobody was in charge. There was no incident commander, so people repeated the same work (two on the database), changed things without telling others (the restart), and nobody asked first what changed recently. The lead was deep in debugging, so support and the product manager got no answer for an hour. Checking recent changes and turning off the flag could have stopped the damage much earlier.
Hint (if the candidate says there is no problem): Between 20:05 and 21:32, who decided what each person should do? And who told support what was going on?
What went wrong? (step by step)
- No declared incident and no roles. Everybody joined, nobody coordinated.
- Duplicate work. Mina and Arash both checked the database, and it took 30 minutes to say “the DB looks fine”.
- An uncoordinated change. The restart at 20:10 hid the errors for a few minutes and made people think it was fixed. Nobody decided it, and it confused the picture.
- Nobody checked recent changes. Most incidents follow a change. The flag from 15:10 was the answer, and it was in the change log all evening.
- The lead was the main debugger. So nobody had the whole picture, and nobody made decisions like “turn off today’s flags”.
- No communication. Support learned from customers. The product manager asked privately, and got no answer. Customers got no status message.
- No scribe. This timeline exists only because the chat was copied later. Many actions are missing from it.
What I would change:
- Declare incidents early, with severity levels agreed in advance.
- Name an incident commander in the first minutes. The IC assigns tasks and does not debug.
- First question for the IC: “What changed in the last 24 hours?” Deploys, flags, configuration, providers.
- A communications role: updates to support and the product manager every 30 minutes, in one channel, with a fixed short format.
- No changes without telling the IC, like the restart.
- Train more people as IC, and practice with a small drill.
- Separate action items for the cause itself: latency alerts on checkout, and rolling out new flags to a small share of traffic first.
Follow-up question: “We are only five people. Isn’t an incident commander too much process for us?”
Follow-up answer:
- Roles are not extra people. In a small team, one person can be IC and communications at the same time.
- It costs one sentence: “I am IC for this one.” It saves the duplicate work you saw here.
- Small teams need it more. When three of five people look at the same graph, there is nobody left for the payment provider or for support.
- Keep it light: a one-page checklist and a status message template are enough to start.
Red flag: The only improvement they suggest is “debug faster” or “better logs”, or they blame Reza for the restart or the person who turned on the flag.
8. A postmortem draft to review
Question: You lead the online shop team. A developer wrote this postmortem draft after the Black Friday checkout incident, and asks you to approve it before it is shared with the company:
Postmortem: Checkout failures on Black Friday
Duration: 20:05 - 21:32
Root cause: Arash turned on the new-fraud-check flag
without testing it properly.
Impact: Many customers could not pay.
Went well: Sara found the problem.
Action items:
1. Arash must test flags properly before turning them on.
2. Be more careful during sales.
3. Improve monitoring.
What do you think about this postmortem? Would you approve it?
Short answer: I would not approve it yet. It blames one person, and it treats human error as the root cause, so the weak points in the system stay. The impact is vague (no numbers), the duration is wrong (the problem started when the flag was turned on at 15:10, not when the alert fired), there is no timeline and no look at the response. The action items are vague and have no owners or dates. I would rewrite it as a blameless review with contributing factors and a few concrete actions.
Hint (if the candidate says there is no problem): Imagine you are Arash and you read this document shared with the whole company. What do you do in the next incident, if you see you made a mistake?
What is wrong? (step by step)
- Blame. Arash’s name in the root cause teaches everyone to hide mistakes. Next time, the person who turned on a flag will stay quiet for an hour.
- “Human error” stops the search. The real questions are: why could one flag break checkout? Why did testing not show it? Why did detection take five hours?
- The duration hides the detection problem. The flag went on at 15:10. Orders were slow for hours before the alert.
- Vague impact. How many checkouts failed? How much revenue was lost? Were any orders charged but not saved?
- No timeline, no response review. The response had no incident commander and no communication. That is half the lesson.
- “Went well” thanks only the lead. Who else helped? What really went well, for example that the flag could be turned off in seconds?
- Vague action items. “Be more careful” and “improve monitoring” cannot be done or checked.
A better version (short):
Impact: about 40% of checkouts failed 20:05-21:32,
checkouts slow since 15:10. Revenue loss: (from finance).
Timeline: 15:10 flag on / 20:05 alert / 20:10 restart (no effect)
/ 21:30 flag found / 21:32 flag off / 23:00 orders fixed
Contributing factors:
- The new fraud check took seconds per order; checkout waited.
- The flag was tested with a few test orders, not real traffic.
- No rule against risky changes on big sales days.
- Alerts on errors only, not on checkout latency.
- No incident commander; recent changes were not checked first.
Action items:
1. Alert on checkout latency. Mina by 5 Dec
2. New flags start at 5% of traffic. Omid by 12 Dec
3. Change freeze on big sales days. Sara by 1 Dec
4. Train two more incident commanders. Reza by 20 Dec
Follow-up question: The director reads the new version and asks: “So who is responsible? Somebody must be responsible.”
Follow-up answer:
- Blameless does not mean nobody is accountable. Accountability means the action items get done, and each one has an owner.
- As the lead, I am accountable for the process that allowed this, for example no rule for flags and no latency alert.
- Arash is accountable for what every engineer owes: honest information and his own action items. He gave the information openly, which helped.
- If we punish the person, people will hide problems, and the next incident takes longer to solve.
- The goal is: the next person who makes the same small mistake cannot break checkout.
Red flag: Keeps the blame, or only removes the name but keeps “human error” as the root cause, or accepts vague action items without owners.
9. A hiring debrief
Question: You lead the shop team and you run the debrief for a backend developer candidate, Omid. Four people interviewed him. This is how the meeting starts:
Scorecards submitted before the meeting: 1 of 4
Head of engineering (speaks first):
"Strong hire. He worked at a big famous company,
and he was very confident."
Interviewer 2: "Yes, I agree, he seemed great."
Interviewer 3: "I asked him about my old project.
We talked for an hour. I liked him."
Interviewer 4 (only written scorecard):
"Coding: 2 of 4. Tests missing, could not
explain his error handling."
Someone: "Let's not waste time. Hire?"
You are running this meeting. What do you think? What would you do?
Short answer: This debrief is not deciding from evidence. Most scores were not written alone before the meeting, so people now follow the first and most senior voice (groupthink and anchoring). The famous company is a halo effect, and “confident” and “I liked him” are feelings, not evidence of skills. Interviewer 3 did not ask the planned questions, so that interview cannot be compared. The only written evidence is a weak coding score. I would pause the decision, ask everyone to write their scores and notes alone first, then discuss each skill of the scorecard, starting with evidence, with the most senior person speaking last.
Hint (if the candidate says there is no problem): If the head of engineering had said “No hire” first, do you think Interviewer 2 would still say “he seemed great”?
Why is this a problem? (step by step)
- Scores are not independent. Three people did not write anything before the meeting. Now their opinion is shaped by what they hear first.
- The most senior person spoke first. Others rarely disagree with their boss in a group. This is groupthink.
- Halo effect. “A big famous company” says nothing about how Omid writes code. One shiny fact makes everything look good.
- Feelings instead of evidence. “Confident” and “I liked him” do not match any skill on the scorecard. Liking is often similarity: people like those who are like them.
- An unstructured interview. One hour on the interviewer’s old project means the planned skills were not checked. It cannot be compared with other candidates.
- The only real data is ignored. The only written scorecard shows a weak coding result, and the group is about to skip it.
- Risk. A bad hire costs the team months. An unfair process also loses good candidates.
What I would do:
- Stop the vote. “Let’s take ten minutes. Everyone writes their score and notes for each skill, alone.”
- Go skill by skill, using the scorecard. For each skill: what did the candidate say or do? Which anchor of the rubric does it match?
- Evidence first. Ask for examples: “What did he do that shows strong coding?”
- Senior people speak last. I ask the head of engineering to share their view at the end.
- Interviewer 3: their skill was not checked. We decide if that missing skill needs a short extra interview.
- Decide by the bar, not by comparing with the last candidate. If we are not sure, the answer is usually no hire.
- After the meeting: a rule for next time. No scorecard before the debrief, no seat in the debrief.
Follow-up question: After you pause, the head of engineering says: “I have hired people for 15 years. I trust my gut.” What do you say?
Follow-up answer:
- Respect the experience. Their observations are useful evidence, so ask them to write them down like everyone else.
- Explain the goal: the same process for every candidate makes hiring fairer and easier to defend, and research says structured interviews predict job performance better than free conversation.
- Make it about the system, not about them: “A gut feeling is a good reason to look closer. What did you see that made you feel that?”
- If they still disagree, the hiring manager owns the decision. Agree on that role before the next debrief.
Red flag: Says “the head of engineering knows best, hire him”, or makes the decision by a quick vote without checking the evidence for each skill.
10. A good developer who slowed down
Question: You lead the shop team. Reza has been on the team for two years and was one of your strongest developers. These are your notes from the last three months:
Month 1: missed the date for the coupon feature (1 week late)
Month 2: PRs smaller and slower, two bugs in production
Month 3: quiet in stand-ups, camera off, not in the retro
Sprint goal missed again because of his ticket
Another lead tells you:
"Put him on a performance improvement plan now.
Write it down and send it to HR this week."
What do you think? What would you do?
Short answer: Something has changed, and I do not know what yet. A strong person who slows down suddenly often has a cause: a personal problem, burnout, unclear expectations, boring or wrong work, or a conflict in the team. Starting with a formal plan skips the most important step: a private, honest conversation. I would talk to Reza in our one-on-one soon, describe what I saw with specific facts, not labels, listen and ask what is going on, then agree on clear expectations and support, and follow up every week. A formal process comes only if nothing improves after clear feedback and real support.
Hint (if the candidate says there is no problem): Reza was strong for two years. What could change a strong person in three months?
Why is the advice a problem? (step by step)
- It treats a symptom, not a cause. We do not know why Reza changed. A formal plan does not fix a sick parent or burnout.
- It skips feedback. Maybe nobody has told Reza clearly what they see. A first formal step without earlier feedback feels unfair, and it is.
- It breaks trust. If Reza has a personal problem and gets a formal warning first, he will probably leave. The team sees it too.
- It loses a strong person. Replacing an experienced developer costs months of hiring and onboarding.
- Waiting too long is also wrong. Three months is already late. The team is affected, so I must act now, just with the right first step.
What I would do:
- Talk soon, in private. In the next one-on-one, not in a stand-up or by chat.
- Facts, not labels. “The coupon feature was a week late, and the last two sprint goals were missed on your tickets. That is not like you.” Not “you are lazy” or “you do not care”.
- Ask and listen. “How are things? Is something making work hard right now?” Then mostly listen.
- Look at my part too. Is the work clear? Did his role change? Is he bored, or blocked by someone?
- Agree on next steps together. Clear expectations for the next weeks, plus support: less load for a while, a different task, time off, or help from HR if it is a personal matter.
- Follow up every week, and write short notes of what we agreed.
- Only if nothing improves after clear feedback and real support, start a formal process with HR. It should not be a surprise for Reza by then.
Follow-up question: In the one-on-one, Reza tells you his father is very ill and he is at the hospital most evenings. He asks you not to tell the team. What do you do?
Follow-up answer:
- Thank him for telling you, and keep it private. Tell the team only what Reza agrees to, for example “Reza has a family matter”.
- Reduce the pressure now: move him off the critical path, take him off on-call for a while, and give him flexible hours.
- Check with HR which leave or support options the company has, and tell Reza about them.
- Protect the team’s delivery in other ways: move his urgent tickets, and adjust the plan with the product manager.
- Keep checking in, and agree when to talk about returning to the normal load.
Red flag: Starts with a formal warning without talking to Reza first, gives feedback with labels instead of facts, or ignores the problem and hopes it goes away.
11. A dashboard to rank developers
Question: The director of engineering wants to “see who is productive”. They show you a dashboard they plan to use for bonuses in all teams, starting next quarter:
Developer Commits Lines added Story points PRs
--------- ------- ----------- ------------ ---
Ali 212 18,400 61 48
Neda 95 6,100 34 21
Reza 41 2,300 18 9
Sara 23 900 12 6
Plan: top 2 per team get a bonus,
bottom 1 gets a performance review.
You lead one of these teams. What do you think? What would you tell the director?
Short answer: These numbers measure activity, not value, and using them to rank people will make things worse. Once a number is a target, people change their behavior to hit the number (this is often called Goodhart’s law): more small commits, more lines, bigger estimates, and less reviewing, pairing and helping others. The person at the bottom may be the most valuable: Sara might be the one who reviews and unblocks everyone. I would suggest measuring the team, not individuals, with delivery metrics like DORA (change lead time, deployment frequency, change fail rate, recovery time), looking at trends, and judging people through goals, feedback and outcomes, not a leaderboard.
Hint (if the candidate says there is no problem): What would you do next quarter if you wanted to be in the top two of this table?
Why is this a problem? (step by step)
- Easy to game. Split one commit into five. Add code instead of deleting it. Give stories more points. The numbers go up, the product does not get better.
- Rewards the wrong thing. Deleting 2,000 lines of dead code is great work, but it looks bad here. So does a careful review that stops a production bug.
- Hides team work. Reviews, mentoring, pairing, incident work and design are not in the table. People who do them drop to the bottom.
- Story points are not comparable. They are a team’s own estimate tool. They differ between teams and between people, so they cannot rank anyone.
- Kills cooperation. If my bonus depends on beating my teammates, I stop helping them.
- Missing quality. Many lines and commits can also mean many bugs. Nothing here shows outcomes for users.
What I would tell the director:
- Agree with the goal. Wanting to see how teams perform is fair. The question is how.
- Measure teams, not people. Use the DORA metrics as a group: throughput (lead time, deploy frequency) with stability (change fail rate, recovery time). Look at trends over months.
- Add outcomes. Did the work move a business goal, for example checkout conversion or fewer support tickets?
- Judge people another way. Clear goals per person, regular one-on-ones, peer feedback and real examples of impact.
- Offer a trial. Run the team dashboard in my team for a quarter, and review what we learned together.
Follow-up question: The director says: “Fine, but then how do I find the low performers?”
Follow-up answer:
- That is the lead’s job, and a lead who works closely with the team already knows. If they do not, that is the real problem.
- A low performer shows up in real things: missed commitments, work others must redo, feedback from teammates, and goals not met.
- Each lead should handle it with clear feedback, support and follow-up, and report to the director with examples, not numbers from a table.
- Numbers can help as a question, not an answer: “Reza’s PRs wait a long time. Let’s find out why.”
Red flag: Accepts the dashboard as a fair way to rank people, or suggests only changing the formula (for example, more weight on story points) without seeing the problem with measuring individual activity.
12. Your first 90 days as the new lead
Question: Next month you become the lead of the shop team. The old lead left suddenly. This is what your manager tells you:
Team: 6 developers (2 senior, 3 mid, 1 junior)
One senior also applied for the lead job
Delivery: one big release every 3 weeks, often late
3 production incidents last month
Reviews: PRs wait about 3 days
Morale: two people told the old lead they are
"thinking about leaving"
Product: the product manager is unhappy about dates
Plan your first 90 days. What do you do first, what do you wait for, and how do you know it is working?
Short answer: Listen first, then fix a few things, then build the system. In the first weeks I do not make big changes: I hold one-on-ones with everyone (starting with the people thinking about leaving and the senior who wanted the job), talk to the product manager and my manager, and learn the code, the release process and the incidents. Then I pick one or two visible problems, like slow reviews and risky big releases, and fix them with the team. After that I set up a steady rhythm: regular one-on-ones, smaller and more frequent releases, a clear incident process, delegation of ownership, and a few team metrics to track progress.
Plan in three parts:
Days 1–30: listen and learn
- One-on-ones with every person. Ask: what works, what is frustrating, what would you change, what do you want to grow in? Start with the two people thinking about leaving.
- The senior who wanted the job. Talk early and openly. Acknowledge the disappointment. Ask what they want, and offer real ownership, for example of the technical direction or of a big area.
- Stakeholders. Meet the product manager and my manager. What does a good result look like for them in three months?
- The system. Read the last incident reports, sit in the release, look at the review queue and the backlog. Do a few small tickets myself to learn the code.
- No big changes yet. I share what I hear, so people see they were listened to.
Days 31–60: a few early wins, with the team
- Share what I learned with the team, and agree together on the top two problems.
- Reviews: any two team members can approve, a team goal of a first review within one day, and smaller PRs.
- Releases: move from one big release to smaller, more frequent deploys through the pipeline, so each one carries less risk.
- Incidents: clear roles during an incident and a blameless review after each one, with owners for the action items.
- Agree with the product manager on how we plan and how we share dates and risks early.
Days 61–90: build the system and grow people
- Delegate ownership. Each senior owns an area, the senior who wanted the role leads technical decisions in theirs.
- Growth plans for each person, from the one-on-ones. The junior gets a mentor.
- Steady rhythm: weekly or every-two-weeks one-on-ones, retrospectives that change one or two real things.
- Measure: a few team metrics, for example review wait time, deployment frequency, change fail rate and number of incidents. Look at the trend.
How I know it is working:
- Reviews wait less and releases are smaller and on time more often.
- Fewer incidents, and the same incident does not happen twice.
- The product manager trusts our dates more.
- In one-on-ones, people raise problems early. Nobody leaves because of the team.
Follow-up question: In week two, the senior who wanted the job disagrees with you in a team meeting, quite sharply, about a technical decision. What do you do?
Follow-up answer:
- Stay calm in the meeting. If they have a good point, say so openly. If the decision is in their area, let them lead it.
- Talk privately after the meeting. Separate the two things: the technical point, and the way it was said.
- Ask how they feel about the new situation. Listen. Their disappointment is normal.
- Agree how you want to disagree: open debate is welcome, the decision is made together, and then everyone supports it.
- Give them real ownership and visibility. Many seniors who missed a lead role do great work as a tech lead or staff engineer.
Red flag: Changes the process, the team or the architecture in the first week without listening, ignores the senior who wanted the job, or plans only technical work and no time with people.
13. Lead time is 9 days. Make the team faster
Question: You lead the checkout team of an online shop. The director says: “Changes take too long to reach users. Make the team faster.” You pull these numbers for the last 3 months (median per pull request):
Step Median
---------------------------- ------
First commit -> PR opened 1.0 d
PR opened -> first review 3.0 d
First review -> merged 1.0 d
Merged -> in production 4.0 d (release every Thursday)
---------------------------- ------
Change lead time 9.0 d
Deploys per month: 4
Change fail rate: 25 %
Open PRs at a time: 11 (team of 5)
What do you see? What would you change first, and how would you know it worked?
Short answer: The team writes code for about 1 day, but each change waits for 7 days: 3 days for a first review and 4 days for the weekly release. So “code faster” will not help. I would remove the waits: agree that reviews come before new work, limit work in progress (11 open PRs for 5 people is too many), keep PRs small, and move from a weekly release to deploying after each merge with a solid pipeline and feature flags. I would watch the trend of lead time together with change fail rate, so we do not trade stability for speed. With small, frequent deploys, the fail rate usually goes down too.
Hint (if the candidate wants to push people to code faster): Which of the four steps is the longest? Is anyone actually working during that step?
What the numbers say (step by step)
- Work vs wait. Coding + review = 2 days. Waiting for review + waiting for release = 7 days. About 80% of the lead time is waiting.
- Too much work in progress. 11 open PRs for 5 people means each person has 2 or more PRs open. People start new work instead of reviewing, so everything waits.
- Big batches. One deploy per week puts many changes in one release. When something breaks, it is hard to find which change did it. This fits the high change fail rate (25%).
- Speed and stability are linked. The same root cause (big, rare releases) makes the team slow and unstable.
What I would do
- Show the team the numbers in the retro and ask what they see. The team owns the fix.
- Reviews first. A team rule: before you start a new item, check if a PR is waiting for you. Aim for a first review within one working day.
- WIP limit. For example, at most 5 open PRs for the team. When the limit is full, help finish instead of starting.
- Small PRs. Split work so a PR can be reviewed in under 30 minutes. Hide unfinished features behind feature flags.
- Deploy on merge. Invest a sprint in the pipeline: good automated tests, a canary or staged rollout, and a one-click rollback. Then stop the Thursday release.
- Measure the change. Track median lead time, pickup time, deploy frequency and change fail rate every week, and compare month by month.
Follow-up question: The director likes it and says: “Great. Let’s give every team a target of 20 deploys per month, and add it to their goals.”
Follow-up answer:
- A target on the number will be gamed: teams can split deploys or deploy empty changes. This is Goodhart’s law.
- Teams have different services and risks, so one number for all is not fair.
- Better: each team looks at its own lead time parts, chooses its own biggest wait, and reports the trend and what it changed. Always next to a stability metric.
Red flag: Proposes overtime, more developers or “estimating better” without looking at where the time goes, or sets a speed target with no stability metric next to it.
14. Every team needs your team
Question: You lead the “Core” team (6 people) of an online shop. Your team owns the database, the payment code, the search service and the deploy pipeline. This is your board for last month:
Requests to Core last month
---------------------------------------------
From Count Example
Checkout 14 "add a column for gift cards"
Catalog 9 "new search filter"
Mobile app 7 "change the payment API"
Marketing 5 "export orders to CSV"
---------------------------------------------
Median wait for a request: 12 days
Planned Core work finished: 20 %
On-call pages for Core: 31
The other teams are angry because they wait for you. Your team is tired. The director asks: “Do you need 4 more people?” What do you answer?
Short answer: More people will not fix it, because the problem is the team design, not the size. Core is in the middle of every change, so every team waits in one queue, and Core holds too many different things to know them well (too much cognitive load). By Conway’s law, this setup also keeps the code tangled. I would split the work by flow: let the stream-aligned teams (Checkout, Catalog, Mobile) own their own changes in their area, turn the shared, stable parts (database setup, pipeline) into a self-service platform with clear docs, and keep only the truly hard part, like payments, as a small specialist team. For a while, Core people can act as an enabling team that teaches the others, then step back.
Hint (if the candidate says “yes, hire more people”): If you hire 4 people, will the Checkout team still need to ask Core before adding a column?
What is wrong (step by step)
- One queue for everyone. Every feature in four teams needs Core, so all work waits in one line (12 days median).
- Too many different things. Database, payments, search and the pipeline are four domains. Nobody can be good at all of them, and on-call is heavy (31 pages).
- No time for the plan. Only 20% of planned work gets done, because requests come in all the time.
- Conway’s law. Because all changes go through one team, the code also grows as one shared center, which makes the next change harder.
- Hiring makes it slower first. New people need months to learn four domains, and existing people spend time on onboarding.
What I would propose
- Map the flow. List which changes go through Core and why. Many are small changes in another team’s own area.
- Give ownership to stream-aligned teams. For example, Checkout owns its own tables and code. Core reviews at first, then only on request.
- Platform as a product. Turn the pipeline and database setup into self-service tools with docs and templates, so teams do not need to ask.
- Keep a small specialist team for payments, which needs deep knowledge and has high risk.
- Enabling first. For one or two quarters, Core people pair with other teams to move the knowledge, then step back.
- Measure it. Watch the wait time for requests, the number of requests to Core, on-call pages, and the planned work finished, every month.
Follow-up question: The Checkout lead says: “We don’t want to own the database. It is not our job.”
Follow-up answer:
- Listen first: they may fear on-call and mistakes. That fear is fair.
- Make it safe: good migration tools, reviews from Core at the start, clear runbooks, and on-call support while they learn.
- Explain the gain: no more 12-day waits, and they decide their own timing.
- Agree on a clear contract: what Checkout owns, what the platform gives, and who is called when something breaks. Review it after one quarter.
Red flag: Only asks for more people, or suggests a better ticket form or priority meeting while keeping every change going through one central team.